Apologies for a lack of recent updates. We now have a finish date of 30 March, just over 5 weeks away. If you have been to the practice in the last week or so you will see the roof is on and most off the windows have been installed. This makes a huge improvement to the exterior appearance. Inside we have plumbers, plasterers and carpenters working.
The lift was installed last week, you can see it in some of the photographs.
The new front door is scheduled to be fitted on 8 March. On that day we will have to ask patients to use the back door. We will make sure it is well signposted.
 |
New lift viewed from first floor |
|
|
 |
First floor admin offices |
|
 |
Last of the internal walls being built. The doorway on the right will be the midwife and phlebotomy room |
|
 |
New waiting room |
 |
View from the waiting room, down the corridor towards the old back door, you can see the lift door on the left |