Thursday, 3 November 2011

New waiting room


Front part of the single storey extension is taking shape.  This will be the new waiting room and the phlebotomist's room.

Inside the first floor has been decorated and we are ready for second fix electrics and radiators to go on.

We will be moving into the new wing on Friday 25 November.

Friday, 14 October 2011

Temporary entrance

Please note for a 4 week period we are using the former staff entrance at the rear of the property for all patients.  Unfortunately this entrance has 7 steps which some of our patients might not be able to manage.  All patients are being informed of this when booking appointments.  If patients are not able to manage these steps we can see them at the Windlesham branch surgery or on a home visit if necessary.

This is only a temporary arrangement before we open the new entrance next month.  Apologies for any inconvenience caused.

Wednesday, 12 October 2011

Drains and water mains

Regular visitors to the practice will have noticed that progress on the disabled access ramp and front of the building seems to have stalled.  We developed a problem with our drains and were keen to make sure we did not build over a man hole cover that might be needed in the future.  Our drains have a history of blocking easily.  This has been mainly due to our neighbours, their drains pass directly under the surgery and merge with ours before reaching the main sewer in the road.

No sooner was that problem sorted than we discovered a problem with our water main.  The pipe installed when the practice was built was only 15mm in diameter, it should be 25mm.  Ir was also only buried 29cm deep, it should at least 75cm according to modern regulations.

You can see in the photo below the new man hole cover to allow access to the drains.  The new water main is the blue pipe and the existing very small bore copper pipe can be seen next to it.

Monday, 26 September 2011

Monday, 19 September 2011

New entrance door


The new entrance doorway is being constructed.  The old waiting room window has been removed and the wall supported ready for a steel support joist to be fitted.  Eventually there will be an automatic glass door fitted.  Before then we will have a temporary wooden door.

Friday, 16 September 2011

Foundations



New foundations for consulting rooms along side Christie Close.

Monday, 12 September 2011

Foundations

The foundations have been laid for the extension on the east side of the building, the side that borders Christie Close  You can start to get an idea of how large the new building will be.  You can also see the outline of the new consulting rooms.  There will 9 brand new consulting rooms on this side of the building, all will be sound proofed as well as three new toilets, a store room and a lift to the first floor. This extension will be single storey.  At first it will look quite stark but once we have re-planted the hedge it should blend in.

Inside the plasterers are finishing off and we can then start decorating and fitting the electrics and radiators.  All the wiring and most of the pipework is in place.

We are holding off moving into the new west wing as the second phase of the works will be more cramped for us and some consultations will need to take place upstairs.  For this reason the contractors are laying the foundations and will build most of the walls before we move over to the new half.