Monday, 14 November 2011

Moving

We have now almost finished phase one of the re-development.  There are just floors to be laid and furniture to be fitted inside.  Outside you can see the canopy taking shape over the front door then the new tarmac surface needs to be laid.

We will move into the new part of the building on Friday 25th November.  On that afternoon the surgery will be closed from 12.30 onwards.  We will continue to offer some appointments and the duty doctor from the branch surgery at Windlesham.  Please phone the usual number.

Thank you for your understanding in the last few weeks.  We know the temporary entrance at the back of the property has been far from ideal.

Thursday, 3 November 2011

New waiting room


Front part of the single storey extension is taking shape.  This will be the new waiting room and the phlebotomist's room.

Inside the first floor has been decorated and we are ready for second fix electrics and radiators to go on.

We will be moving into the new wing on Friday 25 November.

Friday, 14 October 2011

Temporary entrance

Please note for a 4 week period we are using the former staff entrance at the rear of the property for all patients.  Unfortunately this entrance has 7 steps which some of our patients might not be able to manage.  All patients are being informed of this when booking appointments.  If patients are not able to manage these steps we can see them at the Windlesham branch surgery or on a home visit if necessary.

This is only a temporary arrangement before we open the new entrance next month.  Apologies for any inconvenience caused.

Wednesday, 12 October 2011

Drains and water mains

Regular visitors to the practice will have noticed that progress on the disabled access ramp and front of the building seems to have stalled.  We developed a problem with our drains and were keen to make sure we did not build over a man hole cover that might be needed in the future.  Our drains have a history of blocking easily.  This has been mainly due to our neighbours, their drains pass directly under the surgery and merge with ours before reaching the main sewer in the road.

No sooner was that problem sorted than we discovered a problem with our water main.  The pipe installed when the practice was built was only 15mm in diameter, it should be 25mm.  Ir was also only buried 29cm deep, it should at least 75cm according to modern regulations.

You can see in the photo below the new man hole cover to allow access to the drains.  The new water main is the blue pipe and the existing very small bore copper pipe can be seen next to it.

Monday, 26 September 2011

Monday, 19 September 2011

New entrance door


The new entrance doorway is being constructed.  The old waiting room window has been removed and the wall supported ready for a steel support joist to be fitted.  Eventually there will be an automatic glass door fitted.  Before then we will have a temporary wooden door.

Friday, 16 September 2011

Foundations



New foundations for consulting rooms along side Christie Close.