Most of the internal work is now complete. There are some small projects still to complete.
The car park has been delayed somewhat but we hope this will be completed later this week or next. We then will be able to plant the borders outside and remove the heras fencing.
Monday, 28 May 2012
Tuesday, 13 March 2012
New doors
| Previous temporary door |
| New automatic door |
| Alcove made from Dr Saeed's old consulting room |
| New roller racking system in place |
Monday, 20 February 2012
Apologies for a lack of recent updates. We now have a finish date of 30 March, just over 5 weeks away. If you have been to the practice in the last week or so you will see the roof is on and most off the windows have been installed. This makes a huge improvement to the exterior appearance. Inside we have plumbers, plasterers and carpenters working.
The lift was installed last week, you can see it in some of the photographs.
The new front door is scheduled to be fitted on 8 March. On that day we will have to ask patients to use the back door. We will make sure it is well signposted.
The lift was installed last week, you can see it in some of the photographs.
The new front door is scheduled to be fitted on 8 March. On that day we will have to ask patients to use the back door. We will make sure it is well signposted.
| New lift viewed from first floor |
| First floor admin offices |
| Last of the internal walls being built. The doorway on the right will be the midwife and phlebotomy room |
| New waiting room |
| View from the waiting room, down the corridor towards the old back door, you can see the lift door on the left |
Monday, 23 January 2012
Thursday, 12 January 2012
| New insulation |
| Former reception and waiting room, old front door is open |
| New registrar consulting room |
| New registrar's room on right, cleaner's cupboard and toilet |
| One of the new GP consulting rooms |
| New waiting room |
| Stripped out building, former front door on right of photo, looking towards the reception area |
Wednesday, 11 January 2012
The Christmas break is over and the builders are back at work. They are currently working on the new consulting rooms on the ground floor. This has involved excavating new foundations, see previous posts, and building new sound proofed internal walls. The wall that used to look out over the Christie Close side is also being removed once the steel work is in place. Hopefully we can get the roof on before any bad weather.
We now have a fairly accurate finish date from the builders. We hope to be finished by mid March.
| Looking from the room Dr Wilcox used to use out to Christie Close. |
| New floors in the original building |
| Top down view into new consulting rooms |
Wednesday, 14 December 2011
Foundations
New foundations being dug inside the rear part of the surgery. This is the single storey part at the back, nearest the car park. It is the original part of the building and dates back to 1971. It is necessary to dig the foundations to support the new sound proof walls and solid floors.