Monday 26 September 2011

Monday 19 September 2011

New entrance door


The new entrance doorway is being constructed.  The old waiting room window has been removed and the wall supported ready for a steel support joist to be fitted.  Eventually there will be an automatic glass door fitted.  Before then we will have a temporary wooden door.

Friday 16 September 2011

Foundations



New foundations for consulting rooms along side Christie Close.

Monday 12 September 2011

Foundations

The foundations have been laid for the extension on the east side of the building, the side that borders Christie Close  You can start to get an idea of how large the new building will be.  You can also see the outline of the new consulting rooms.  There will 9 brand new consulting rooms on this side of the building, all will be sound proofed as well as three new toilets, a store room and a lift to the first floor. This extension will be single storey.  At first it will look quite stark but once we have re-planted the hedge it should blend in.

Inside the plasterers are finishing off and we can then start decorating and fitting the electrics and radiators.  All the wiring and most of the pipework is in place.

We are holding off moving into the new west wing as the second phase of the works will be more cramped for us and some consultations will need to take place upstairs.  For this reason the contractors are laying the foundations and will build most of the walls before we move over to the new half.